Vale NC
Location
New Caledonia
Project
Major Shutdown – Supply of Personnel A5:H10 Equipment – Boiler and Acid Plant
Work carried out:
ICBS subcontracted to APMS as the head contractor to assist with the execution of a major shutdown on the acid plant, associated heat exchangers and boiler. This scope of work involved the mobilisation of 50 x personnel of various skills including Project Management, Supervision, Quality Control and Inspection, Coded Welding and Boilermaking / pipefitting.
Vaue:
$1,500,000
Completion Date:
2019
Duration:
18 Days
Achievements:
Completed on time with no injuries or incidents