BHP Nickel West
Location
Kwinana Western Australia
Project
Major Shutdown – Supply of Personnel and Equipment – Boiler and Acid Plant
Work carried out:
ICBS subcontracted to APMS as the head contractor to assist with the execution of a major shutdown on a boiler, associated heat exchangers and equipment including tanks, valves and pipework. This scope of work involved the mobilisation of 25 x personnel of various skills including Project Management, Supervision, Quality Control and Inspection, Coded Welding and Boilermaking / pipefitting.
Vaue:
$450,000
Completion Date:
2019
Duration:
5 Days
Achievements:
Completed on time with no injuries or incidents