Client

BHP Nickel West

Location

Kalgoorlie

Project

Minor Shutdown – Supply of Personnel and Equipment for Heat Exchanger and Boiler Inspection and Repairs

Work carried out:

ICBS subcontracted to APMS as the head contractor to assist with the execution of a minor shutdown on a boiler, associated heat exchangers and equipment. This scope of work involved the mobilisation of 15 x personnel of various skills including Project Management, Supervision, Quality Control and Inspection, Coded Welding and Boilermaking / pipefitting.

Vaue:

$153,000

Completion Date:

2019

Duration:

5 Days

Achievements:

Completed on time with no injuries or incidents